SEZ/EPZ Licensing Procedures

 

  • Investor initiates the process by making an inquiry with EPZA to confirm investment procedures, eligibility criteria and availability of factory space or serviced land.

 

  • Investor submits a project proposal and application form which is completely filled to EPZA with a non-refundable fee of US$ 300.

 

  • EPZA evaluates the project proposal and provides the investor with a letter of approval in principles, this takes 3 days.

 

  • Environmental assessment of the premises/land so as to be able to obtain environmental approval                                (Where required)

 

  • For zone development, EPZA facilitates declaration of the land which is done by the Minister for Industry and Trade. 

 

  • Investor pays relevant license fees and obtains SEZ / EPZ license. The license fee for SEZ / EPZ developer is US$ 5,000 for three years. While annual fee for SEZ / EPZ user is US$1,000 per year payable three years consecutively.
 
  • Investor begins operations.

 

Notice to EPZA investors on changes of Investment Services fees.

 

 Click here to view new Investment facilitation Services Fees

 

IMPORTANT DOCUMENTS FOR NEW INVESTMENT ASSESSMENT PROCEDURES:


Click here to view the list of important documents for assessment procedures of new investment



A word from DG

  On behalf of the entire team, I am pleased to welcome all esteemed Investors to the EPZA..

Read more...
Latest News & Events

KEEP IN TOUCH WITH US


       Export Processing Zones Authority,

       Benjamin William Mkapa SEZ,
       Mabibo External.
       P.O.Box 12112
       Dar es Salaam - Tanzania.
       
      Tel :  
   +255 (0)22 2925058-60
       Fax :    +255 (0)22 2925061
       E-mail:   info@epza.go.tz